Saturday, 16 December 2017 14:29

Construction Works Updates at Mount Pleasant Station for December 15th

 

 

Installation of Piles on North Side of Eglinton

Crews at Mount Pleasant are installing piles on the north side of Eglinton Avenue East. Once work has commenced on these piles, it cannot be interrupted and therefore must be completed.

Due to unforeseen circumstances, tonight's concrete pour is expected to continue past 11:00 p.m.We apologise for any inconvenience this work may cause.
 

Launch Shaft Construction at Taunton

A concrete pour for the launch shaft construction at Taunton Road was completed today, Friday, December 15th. Please note, the use of a generator is required to keep the concrete warm. With this in mind, the generator will be active overnight tonight. However, it will not be operational over the weekend (Saturday and Sunday).

The generator usage will resume overnight next week, for approximately two (2) nights. More details to follow.
 

Construction Notice - Taunton Road Closure and Storm Sewer Installation

Please consider reading the construction notice for more details:
http://thecrosstown.ca/news-media/whats-new/closure-of-taunton-road-for-storm-sewer-installation-at-mount-pleasant-station

Eglinton - Mt. Pleasant CLC Presentation Material

Eglinton - Mt. Pleasant Construction Liaison Committee (CLC) Meeting
The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on November 14, 2017.

To view the presentation, please click the link below:
http://thecrosstown.ca/news-media/whats-new/eglinton-mount-pleasant-construction-liaison-committee-meeting-3
 

A Look Ahead: December 2017 & January 2018

Older News

Older news can be found in the closed discussion forum.

Member businesses can now upload their own banner

E-Newsletter

Stay in the Loop and get updates from the BIA by E-Newsletter.

Please let us know your name.

Please let us know your email address.

Member businesses can now upload their own banner