Monday, 08 January 2018 19:36

Update on Works and Upcoming Traffic Changes at Mount Pleasant Station

 

What Work is Taking Place?

  • Since Fall 2017, crews have been undertaking utility and support of excavation work at Mount Pleasant Station. Below is the status of work that has been completed and work that is still ongoing:

    Complete:

  • Hydro vault work at the southeast corner of Mount Pleasant Road and Eglinton Avenue East.
  • Ongoing:

  • Pile installation on the north side of Eglinton Avenue East.
  • Sewer relocation at the northeast corner of Mount Pleasant Road and Eglinton Avenue East, and at 801 Mount Pleasant Road.
  • Launch shaft construction for storm sewer installation at Taunton Road and Eglinton Avenue East. Learn more>>

Upcoming Work and Construction Staging: January 2018

  • Starting January 2, 2018, crews will mobilize new equipment, including a generator, pumps, and a micro tunnel boring machine (TBM), to the launch shaft site at Taunton Road. This equipment is required for storm sewer installation.

    Starting January 8, 2018, the TBM will be in placed into the launch shaft, and micro-tunnelling and pipe installation will begin. Storm sewer installation will take place on a 24/7 basis for approximately three (3) weeks, including use of surface equipment .  

    Simultaneously, a new work zone will be erected on the south side of Eglinton Avenue East, east of Brownlow Avenue to make way for construction of the receiving shaft, where the TBM will be extracted. In advance of constructing the receiving shaft, crews will perform Bell utility relocation in the work zone. Temporary sidewalk closures may be in effect.

    Access to Taunton Road at Eglinton Avenue East will be reinstated in March 2018, once storm sewer installation is complete.

    Construction staging as early as January 8, 2018:

Hours of Work

Utility and Support of Excavation:

  • Permitted hours of work are 7:00 a.m. to 11:00 p.m.Monday through Sunday.
Storm Sewer Installation: 
  • Work will occur 24 hours a day, seven days a week for approximately three (3) weeks.

What to Expect

  • Noise from construction activity and equipment, as well as site lighting can be expected.
  • While mitigation measures will be in place, overnight noise can be expected.
  • Taunton Road will remain closed at Eglinton Avenue East.
  • The north-south crosswalk on the east side of the Mount Pleasant-Eglinton intersection will remain closed for the duration of this stage.
  • Sidewalk closures may be in effect.
  • Pedestrian rerouting around work zones can be expected.
  • Signage will be placed to advise motorists and/or pedestrians of any changes.
  • Pedestrians and road users can expect delays when travelling through the work zone.
  • As always, please take care when travelling near work sites.

Transit Information

Relocation and re-routing of bus stops is done in consultation between TTC and Metrolinx to ensure construction can continue safely while minimizing impact on the community and customers. Please watch for posted notices indicating new information. 
 

Travelling Smart During Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.
 

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor. real-time traffic and transit information for the Eglinton corridor.
 
For more information, please contact Phil Rodriques at the East Community Office.
Thank you for your continued patience as we work to build this important project.
Please support your local businesses during construction.

Older News

Older news can be found in the closed discussion forum.

Member businesses can now upload their own banner

E-Newsletter

Stay in the Loop and get updates from the BIA by E-Newsletter.

Please let us know your name.

Please let us know your email address.

Member businesses can now upload their own banner